St. Boniface General Hospital: Emergency Power Upgrade
Location: 409 Tache Avenue, Winnipeg, Manitoba
The addition of a new 2 mega-watt diesel generator to the SBGH powerhouse included modifications of the existing generator building with the
installation of a new inertia pad, removal of exterior wall section, replacement of the existing underground main fuel storage tank & day tanks as well as extensive coordination to parallel the new switchgear and control modifications with the hospitals existing equipment.
Delivery Method: Construction Management
Contract Value: $2,375,884
Year Completed: 2010
Consultant: Stantec Architecture Ltd.