The addition of a new 2 mega-watt diesel generator to the SBGH powerhouse included modifications of the existing generator building with the
installation of a new inertia pad, removal of exterior wall section, replacement of the existing underground main fuel storage tank & day tanks as well as extensive coordination to parallel the new switchgear and control modifications with the hospitals existing equipment.

Delivery Method: Construction Management

Contract Value: $2,375,884

Year Completed: 2010

Consultant: Stantec Architecture Ltd.